120 tons, One Vessel, One Bill of Lading, and a Reduced Carbon Footprint

Case Studies

Challenge

A food industry technology supplier won a contract to supply a complete processing plant for a Middle Eastern potash producer. The items were being manufactured in Central Europe and needed to be transported to the final destination. The cargo included a rotary drum exceeding 120 tons in weight and 5 meters in diameter, in addition to another 369 pieces of both in-gauge and out-of-gauge (OOG) cargo.

The challenge? Loading all in-gauge pieces into containers under one bill of lading and shipping the cargo directly to the port of discharge.

Solution

    • Vessel scheduling
    • Container leasing
    • Cargo planning & design
    • Ocean charters
    • Documentation
    • Visibility & reporting

 

Benefits

  • All components were combined into a single shipment.
  • Leased containers allowed the customer to reduce costs and liability.
  • Since all cargo was transported on a barge, as opposed to trucks, the customer avoided carbon emissions.

The customer achieved more than $25,000 in transportation cost savings.

Transporting oversized cargo?

OIA Global has a dedicated team handling out-of-gauge renewable energy cargo.