Moving Out of Gauge (OOG) Renewable Energy Cargo Through Narrow Mountains

Case Studies

Challenge

Transporting a 113-ton rotor shaft from a factory in Switzerland through narrow mountain passes and tunnels to a hydropower site in northern Italy. This became even more complicated because the two countries had different rules for convoy transportation, requiring an exchange of vehicles at the border.

Solution

Benefits

  • The rotor shaft was safely delivered to its end destination without incident
  • Route surveys for preemptive contingency planning
  • Communication with road authorities in both countries

OIA's project logistics team transported a 113 metric ton rotor shaft from a factory in Switzerland to a hydropower site in northern Italy.

Moving oversized cargo?